Well, we had a meeting with our site supervisor to run through the defect report. The site supervisor agreed to fix probably 3/4 of the issues. The issues they disagreed with, when checked with Howard Ryan, were actually building code violations and we've told Eden Brae in writing we still need the other issues rectified.

The construction manager is now meeting with the site supervisor onsite to run through the other problems, so fingers crossed this issue doesn't need to get escalated further.

This experience is our first genuinely unhappy experience with Eden Brae.