Kath and Jamie's Eden Brae Homes building experience

Our experience building in Sydney with Eden Brae Homes

Sunday, December 21, 2008

Landscaping complete

›
The landscaping is complete and most of the maintenance items have been taken care of. Mind you, it did take some time, but probably because...
2 comments:
Wednesday, October 29, 2008

Maintenance Inspection

›
We had our maintenance inspection today. There were only about 15 things on the list. Most of the issues are from movement as the house sett...
2 comments:
Saturday, September 13, 2008

Landscaping proceeding...a bit slowly

›
Our landscaping is progressing slowly. The landscaper has a couple of large jobs at the moment so we're all sharing. Here are some photo...
7 comments:
Monday, July 28, 2008

Wrong Fireplace installed!!

›
We realised this week that the fireplace installed is not the one we paid for. We paid for the top model from JetMaster and instead received...
12 comments:
Wednesday, July 23, 2008

We settled....now to finish off

›
We settled last week with only a couple of minor issues. The laundry tap needs to be replaced because it is the wrong one and the exhaust fa...
2 comments:
Wednesday, July 16, 2008

Poor and Good Service

›
Yesterday we had another look at the premises and found a lot of faults still weren't rectified from the the pre-handover inspection of ...
4 comments:

Liquidated Damages

›
Yesterday we received notice of our liquidated damages. Basically, after taking an extra 22 weeks than the contract sign date, they've c...
1 comment:
›