Last week's photos corrupted, but as this week's photos show, the brickwork is about half done. The brickwork progress claim arrived in the mail last Monday - a fair bit early. A quick phone call to the accounts section and everything was sorted.
Sunday, November 25, 2007
Sunday, November 4, 2007
Taps fixed and frame pretty much complete
The windows for the front facade have been installed and the taps have been relocated to the correct location. Brickwork was expected to start during the previous week but has obviously been put off for a week.
Front facade with the windows installed.
No taps between rumpus windows anymore.
Taps are now located between these two windows. It's hard to see from the photo, but they are there.
Front facade with the windows installed.
No taps between rumpus windows anymore.
Taps are now located between these two windows. It's hard to see from the photo, but they are there.